A regular meeting of the Board of
Adjustment of the Township of Roxbury was held on the above date at 7:30 p.m. with Chairperson Gail Robortaccio presiding. After a salute to the Flag, Ms.
Robortaccio read the “Open Public Meetings Act”.
BOARD MEMBERS PRESENT: Gail
Robortaccio, Mark Crowley, Joyce Dargel, Barbara Kinback.
ABSENT: Robert Kurtz, Peter
Giardina, Sebastian D’Amato, Heather Darling, Candy DeVenezia.
PROFESSIONAL STAFF PRESENT:
Larry Wiener, Russell Stern.
Also present: Dolores DeMasi, Board
Secretary.
Minutes of 10/16/06
Ms. Dargel made a motion to
approve the minutes. Mr. Crowley seconded.
Roll as follows: Ms. Dargel,
yes; Mr. Crowley, yes; Ms. Kinback, yes; Ms. Robortaccio, yes.
RESOLUTIONS
BA-53-06 – 52 MAIN ST. – FINAL
SITE PLAN FOR PROPERTY LOCATED ON MAIN ST. BLOCK 520, LOT 7, 8, 9, 12 & 13
IN B-1 ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP
OF ROXBURY
RESOLUTION
WHEREAS,
the Board, after carefully considering the evidence presented by the applicant
and having conducted a public hearing has made the following factual findings:
- The applicant is the owner
of the premises that contains an office building in front and town houses
in the rear.
- Applicant is seeking final
site plan approval for the site that received preliminary approval in
1998.
- Prior to the public
hearing, the Board received a Final Site Plan (1 sheet) prepared by Schoor
DePalma revised to 6/30/06.
- The Board received the
following reports:
- Russell Stern, the
Township Planner, dated 8/2/06, updated to 10/12/06
- John Hansen, the Township
Engineer, dated 10/9/06
- The project was partially
constructed by a prior owner. This developer acquired the site and is
seeking to complete the project in accordance with the preliminary site
plan approval.
- The Board’s Engineer
presented his report dated 10/9/06 regarding the status of the project and all open
items for review with the applicant. The applicant is requesting waivers
from items 4, 5, 9(b).
- The freestanding sign is
located only 13’9” from the front setback although the preliminary
approval requires and the site plan shows 15’. Since the setback requirement
is 10’, the Board considers this a de minimis variation.
- The applicant either has
complied or will comply with the remaining items on the engineer’s report.
- The Board Planner presented
his report dated 10/12/06 for review with the applicant. The applicant is
requesting a waiver from item 10 regarding installation of a paver
sidewalk beneath the front office overhang. Applicant agrees that any
replacement of the existing concrete sidewalk will be pavers.
- Applicant either has
completed or will comply with the remaining items in the planner’s report.
- Applicant has sent a form
of deed restriction addressing COAH affordability controls to the Board
attorney for review.
WHEREAS,
the Board has determined that the relief requested by the applicant can be granted
without substantial detriment to the public good and without substantially
impairing the intent and purpose of the Zone Plan and Zoning Ordinance of the
Township of Roxbury for the following reasons:
- The Board finds that the
requested waivers are reasonable. The non-compliance with the preliminary
site plan approval was done by the prior owner. The Board finds that this
developer is making diligent efforts to bring the site into compliance and
has requested waivers only on items where it would be unreasonably
burdensome to comply.
- Allowing the waivers would
permit the project to be completed and bring the subject site back into
use.
- The proposed use will have
no impact on the surrounding properties or on the zone plan or Zoning
Ordinance.
NOW,
THEREFORE, BE IT RESOLVED by the Board of Adjustment of the Township of Roxbury on
the 16th day of October 2006 that the approval of the within application
be granted subject, however, to the following conditions:
- Subject to the review
and/or approval of all other governmental agencies and/or enteritis with
joint and/or concurrent jurisdiction over the within premises and the
development thereof.
- Payment of all fees,
sureties and/or escrows required by Ordinance or prior approvals.
- Applicant shall comply with
all comments or conditions of the Board Engineer’s report dated 10/9/06 and in
particular:
- Drainage swale to be field
verified by Board’s engineer.
- Applicant shall provide a
properly constructed overflow grate on the underground storm water
detention system.
- Applicant shall provide an
“as built” survey (same to be in hard copy and digital format) showing
the dimensions between the two principal structures to be at least 30
feet.
- Applicant to install bench
between the two structures.
- Applicant to provide
documentation that it has requested Title 39 enforcement on-site.
- Applicant shall comply with
all comments or conditions of the Board’s Planner’s report dated 10/12/06 and in
particular:
- Provide documentation
(deed) to the Township Attorney showing compliance with COAH
Affordability Controls. Same is a condition precedent to the issuance of
a certificate of occupancy.
- Applicant to install
depressed curbs.
- Fire Lane striping to be
provided.
- Basement area of the 2
market rate units shall be utilized for storage only- NO LIVING SPACE.
- Back-shields to be
provided on all free-standing lights to prevent off-site glare.
- Final landscaping
including deviations from the original plans to be reviewed and approved
by the Township Planner.
- All conditions of the
prior approval not specifically waiver or modified continue in full force
and effect noting in particular:
1.
The use is limited to four
residential units- one low income, one moderate income, two market rate units,
and the commercial use- Offices- shall not exceed 4,106 square feet. All COAH
regulations as set forth in the Municipal Ordinance 13-7.826 et seq. shall be
complied with. All compliance and/or regulatory fees shall be paid by the
applicant. (see Paragraph 25. et seq. of Stern report dated 10/12/2006 update)
2.
Attic Area in the commercial
structure to be used for storage only.
3.
Architecture and site amenities
(lighting, signage, benches, paving, sidewalks) shall be historical in context.
4.
“52 Main Street” shall be
identified on the free standing sign and the applicant shall provide “caps” on
the monument sign posts. Sign to be located in a conforming location.
Ms. Dargel made a motion to
approve the resolution. Mr. Crowley seconded.
Roll as follows: Ms. Dargel,
yes; Mr. Crowley, yes; Ms. Robortaccio, yes.
BA-57-06 – WEST CHESTER MACHINERY – FINAL SITE PLAN FOR
OFFICE/WAREHOUSE LOCATED ON OLD LEDGEWOOD RD. BLOCK 9303, LOT 7 IN B-1A ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP OF ROXBURY
RESOLUTION
WHEREAS,
the Board, after carefully considering the evidence presented by the applicant
and having conducted a public hearing has made the following factual findings:
- The
applicants are the owners of the premises that contain a retail/office use
and warehouse.
- Applicant
is seeking final site plan approval for the site after receiving use
variance in 2001 and preliminary site plan approval in 2003.
- Applicant
is seeking final site plan approval for the construction of a 4,800 square
foot warehouse addition to the existing facility.
- Prior
the public hearing, the Board received the following plans:
Prepared by G.
Gloede and Associates
Sheet 1, Final Key Map & General Notes, revised
5/8/06
Sheet 2, Final Site Plan, revised 5/8/06
Sheet 3, Profiles, revised 5/8/06
Sheet 4, Soil Erosion & Sediment Control revised
5/8/06
Sheet 5, Soil Erosion Notes and Details, revised
5/8/06
Sheet 6, Construction Details, revised 5/8/06
Prepared by
Edward F. Secco
Sheet 1 of 1, Existing Conditions, dated 1/10/06
- The
Board received the following reports:
- Russell
Stern, the Township Planner, dated 10/12/06
- John
Hansen, the Township Engineer, dated 10/12/06
- The
Board Planner presented his report dated 10/12/06 regarding the status of
the project and open issues for review with the applicant. Applicant has
complied or agrees to comply with all conditions contained therein.
- The
Board Engineer presented his report dated 10/12/06 regarding the status of
the project and open issues for review with the applicant. Applicant has
complied or agrees with all conditions contained therein.
- Applicant
agreed to replace one wallpak light mounted on the side of the building
with a shoebox type fixture.
WHEREAS,
the Board has determined that the relief requested by the applicant can be
granted without substantial detriment to the public good and without
substantially impairing the intent and purpose of the Zone Plan and Zoning
Ordinance of the Township of Roxbury for the following reasons:
- The
Board finds that the applicant has complied with or substantially
completed all items requested by the Board Planner and Engineer.
- The
completed project will have no impact on the surrounding properties or on
the zone plan or Zoning Ordinance.
NOW,
THEREFORE, BE IT RESOLVED by the Board of Adjustment of the Township of
Roxbury on the 9 th day of November
2006 that the approval of the within application be granted subject, however,
to the following conditions:
- Outdoor
storage shall only be allowed in conjunction with and accessory to the
principal use conducted on the property. In addition, all outdoor storage
shall not exceed a height of 14’.
- All
vehicle maintenance activities shall be performed within the building and
there shall be no fuel transfer or dispensing of fuel permitted on site.
All oil solvents, anti-freezes, and the like shall be stored indoor within
containment systems approved by the Roxbury Township Health Department.
- All
conditions and recommendations of the Board’s Engineering
Consultant and the Municipal Planner as set forth in their reports and as
testified to and/or stipulated on the record and in particular:
- Salt
shed shall be setback 20 feet from the rear property line and 10 feet
from the side property line.
- A
conforming dumpster enclosure on a concrete pad with board-on-board
fencing shall be provided and set back ten feet from the rear property
line.
- Walpak
lights located on the building shall be replaced with shoebox type
fixtures.
- The
timber rack pipe shall be no higher than fourteen feet.
- Payment
of all fees, sureties, and escrows required by Ordinance.
- Continued
compliance with all conditions of the prior approvals including but not
limited to:
1. Outdoor storage shall only be allowed in
conjunction with the principal use conducted on the property. In addition all
outdoor storage shall not exceed a height of 14 feet.
2. The applicant shall comply with the well testing
and reporting requirements as set forth in the 1992 resolution and reiterated:
Applicant shall perform well testing once per year to test volatile organic
compounds using USEPA method 502-1 and 502-2 and test for inorganic chemical
analysis, if needed. The results of this testing shall be submitted to both the
Netcong and Roxbury Township Environmental Commission. Upon three tests showing
no groundwater pollution, no further testing shall be required. This condition
does not relieve the applicant from compliance with all rules and regulations
of the Environmental Commission or other governmental agency with joint and/or
concurrent jurisdiction.
g. Prior to the issuance of a Certificate of
Occupancy:
1. An “as built” survey (hard copy and CAD digital
format) showing installation of all site improvements to be submitted to the
Township Engineer.
2. Certification from the Board of Health on the
abandonment of the septic system for the razed building.
- Subject
to all other governmental agencies with joint and/or concurrent jurisdiction
over the subject premises and the within application.
Mr. Crowley made a motion to
approve the resolution. Ms. Dargel seconded.
Roll as follows: Mr. Crowley,
yes; Ms. Dargel, yes; Ms. Robortaccio, yes.
BA-30-06 – 1ST
BAPTIST CHURCH OF LEDGEWOOD – SITE PLAN FOR ALL PURPOSE ROOM LOCATED ON MAIN
ST. BLOCK 6406, LOT 4/5 IN B2/R3 ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP OF ROXBURY
RESOLUTION
WHEREAS,
the Board, after carefully considering the evidence presented by the applicant
and having conducted a public hearing has made the following factual findings:
- Richard
Wade, Esquire represented the applicant.
- The
applicant is a religious institution. It previously received a use variance
(9/12/05) and the present application is for site plan approval.
- The
applicant submitted the following documents with the application:
Prepared by
Nicholas J. Wunner
Sheet 1, Cover Sheet/Variance Map,
revised 7/25/06, 10/2/06
Sheet 2, Grading and Drainage, revised
7/25/06, 10/2/06
Sheet 3, Soil Erosions and Sediment Control Plan,
revised 7/25/06, 10/2/06
Sheet 4, Soil Erosion and Sediment Control Plan Notes
and Details, revised 7/25/06, 10/2/06
Sheet 5, Lighting and Landscaping, revised 7/25/06,
10/2/06
Sheet 6, Existing Conditions/Slopes, revised 7/25/06,
10/2/06
Sheet 7, Construction Detail Sheet, revised 7/25/06,
10/2/06
Prepared
by Charles Schaffer Associates, Inc.
Sheet
A-1, Elevations, revised 7/25/06, 9/28/06
Sheet
A-2, Elevations, revised 7/25/06, 9/28/06
Sheet
A-3, First Floor Plan, revised 7/25/06, 9/28/06
Sheet
A-4, Second Floor Plan, revised 7/25/06, 9/28/06
- The
Board received the following memorandums:
- Russell
Stern, the Board’s Professional Planner, dated 6/7/06 with an 8/2/06
update and a 10/13/06 memo.
- John
Hansen, the Board’s Professional Engineer, dated 6/7/065, revised
8/14/06.
- Richard
D. Cramond, Historic Advisory Committee, dated 6/29/06.
- The
subject property consists of two tax lots designated 4 & 5. The total
site encompasses 2.1 acres and is located partially in the R-3 Single
Family Zone and the B-2 Highway Business District. The B-2 Zone fronts
Route 46 and the R-3 Zone is situated along Main Street. Entry into the
site is provided from Main Street. The property presently contains a
church, a single family dwelling, and a parish office all of which are
located within the R-3 Zone portion of the property. An existing parking
lot play area and garage are situated in the B-2 Zone. It is also noted
the site is located within the Township’s Historic District and a church
is a permitted conditional use in both the R-3 and B-2 Zone Districts.
- The
main street area of the church adjoins residentially developed
properties. To the northwest along Route 46 the adjoining property is an
auto body shop and to the southeast is a branch of the Bank of New York.
- As
noted, the applicant is presented before the Zoning Board with a request
for preliminary site plan approval for an 8,100 square foot two-story
all-purpose building. The applicant would be demolishing the existing
garage. The first floor of the proposed building would be 6,600 square
feet and contain a gymnasium and four classrooms. There would be a second
floor of 1,500 square feet, which would contain one classroom and a 36’4”
x 25’ multi-purpose room. It is proposed that the existing parking lot
would continue to accommodate parking generated by the new
infrastructure.
- At
the first public hearing, the applicant offered the testimony of Reverend
David Hallwick. Reverend Hallwick is a spiritual leader of the church.
He gave a general overview of the project and explained the church’s
vision for the use of the property and how the new structures would tie
into church activities. He also noted that there had been a meeting with
the Historic Advisory Committee and the ultimate design that was being
presented was based upon concerns raised by the Historic Advisory
Committee.
- The
applicant’s second witness was its architect, Mark Bak. Mr. Bak was an
employee of the architectural firm, Charles Schaffer Associates, which
prepared the architectural plans for the project. Mr. Bak reviewed the
architectural features and design of the project.
- The
applicant’s third witness was its project engineer, Nicholas Wunner. Mr.
Wunner presented exhibit A-1 (a colorized version of Sheet 2 of his
engineering submissions). He provided the Board with an overview and did
a “walk-through” of the different features and elements of the site.
- Mr.
Wunner concurred that the plans, as drawn, indicated the applicant would
need a design waiver from Section 13-8.610 of the Roxbury Zoning Ordinance
in that no sidewalks were be provided in front of the existing dwelling.
- The
matter was continued to a future public hearing date.
- The
matter was continued to the 8/13/06 public hearing. At that time, the
applicant’s engineer, Nicholas Wunner, was recalled. Mr. Wunner reviewed
the updated report of John Hansen. The applicant’s engineer and the
Board’s engineer resolved the engineering issues. Mr. Wunner also
introduced into evidence exhibits A-2, A-3, and A-4, which were photos of
the existing site from different perspectives.
- The
applicant next recalled its architect, Mark Bak. Mr. Bak presented
colorized elevation drawings (exhibit A-5), which showed revised
architectural renderings. The architectural detail had been commented
upon in Mr. Stern’s revised report and Richard Crammond of the Historic
Advisory Committee was also present at the meeting. Both Mr. Stern and
Mr. Crammond opined that the new architectural elevations were actually a
step “backward” from the prior renderings.
- Reverend
Hallwick was recalled and stated the applicant would attempt to work with
the municipality to revise the architectural plans. The matter was
carried to a future public hearing.
- The
matter was continued to the 10/16/06 public hearing. At that time, the
applicant recalled its engineer and architect.
- Applicant’s
professionals reviewed the reports of the Board’s engineer and planner.
After discussion, all outstanding engineering, planning, and architectural
issues were resolved.
WHEREAS,
the Board has determined that the relief requested by the applicant can be
granted without substantial detriment to the public good and without
substantially impairing the intent and purpose of the Zone Plan and Zoning
Ordinance of the Township of Roxbury for the following reasons:
- The
Board finds the applicant’s professionals to be credible and reasonable in
resolving issues raised by the Board’s engineer and planner.
- With
no remaining site plan issues, the Board finds that it is appropriate to
grant preliminary site plan approval.
NOW,
THEREFORE, BE IT RESOLVED by the Board of Adjustment of the Township of
Roxbury on the 16th day of October, 2006 that the approval of the within
application be granted subject, however, to the following conditions:
- Applicant
shall comply with all recommendations of the planner and engineer as
agreed to at the public hearing and in particular the following:
- Applicant
to provide details of physical connection between the drywells.
- A
tee-wye and concrete splash block overflow detail shall be revised to
incorporate to show the tee connection to be above grade.
- Leader
drain piping size and slope detail to be provided to be documented to
confirm it is adequate for 100-year storm.
- Mechanical
pad and location to be detailed on plans.
- All
landscaping shall be reviewed and approved by the Township Planner
including but not limited to replacement trees.
- All
lighting fixtures to be field inspected to verify compliance with
Township lighting specifications. The light base shall be set back a
minimum of 2.5 feet from the edge of pavement.
- Pavement
repair detail to be reviewed and approved by the Municipal Engineer.
- Construction
access shall be coordinated with current operations on-site.
- Subject
to availability of water and sewer.
- Applicant
shall secure a tree removal permit.
- Lots
4 and 5 shall be merged.
- As
applicable, the applicant shall provide their pro-rata share of off-tract
and off-site improvements as determined by the Township Engineer.
- As
applicable, the applicant shall pay a mandatory development fee.
- On
the front and right side elevations the applicant will exercise their
best efforts to match the stone on the Church and will utilize a smooth
faced color concrete block along the rear and left side elevations.
- The
applicant shall obtain a tree removal permit prior to site
disturbance/tree removal.
- A
performance bond shall be posted for replacement trees prior to the
issuance of a Tree Removal Permit.
- Payment
of all fees, sureties, and escrows required by Ordinance.
- Subject:
to the review and/or approval of all other governmental entities and/or
subdivisions thereof with joint and/or concurrent jurisdiction over the
within application.
Ms. Dargel made a motion to
approve the resolution. Mr. Crowley seconded.
Roll as follows: Ms. Dargel,
yes; Mr. Crowley, yes; Ms. Robortaccio, yes.
BA-55-06 – VIRGINIA GUIDER
– VARIANCE TO REPLACE SHED IN FRONT YARD LOCATED ON KINGSLAND RD. BLOCK 11002,
LOT 6 IN R-3 ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP OF ROXBURY
RESOLUTION
WHEREAS,
the Board, after carefully considering the evidence presented by the applicant
and having conducted a public hearing has made the following factual findings:
- The
applicant is the owner and occupant of the single-family home on site.
- The
subject premise is a lake front property.
- Applicant’s
home faces the lake though it is accessed from Kingsland Road. As a
result, the front and rear yards are de facto reversed.
- Applicant
is proposing to construct a 10’x10’ shed in the de facto rear
yard. Applicant showed photographs of the property.
- Applicant
received a letter of denial dated 8/8/06 from Tom Potere, the Zoning
Officer.
WHEREAS,
the Board has determined that the relief requested by the applicant can be granted
without substantial detriment to the public good and without substantially
impairing the intent and purpose of the Zone Plan and Zoning Ordinance of the
Township of Roxbury for the following reasons:
- The
Board finds that because of the way the house faces the lake, the real
rear yard is on the street. There are several other houses in the area
that are similarly situated and have sheds on the street side.
- The
proposed relief is consistent with the intent and purpose of the Zone Plan
and Zoning Ordinance. In reality, the shed is a rear yard amenity.
NOW,
THEREFORE, BE IT RESOLVED by the Board of Adjustment of the Township of
Roxbury on the 16th day of October 2006 that the approval of the within
application be granted subject, however, to the following conditions:
1.
Shed to be sized (10’ x 10’) and
located as depicted on the plans submitted with the application.
Mr. Crowley made a motion to
approve the resolution. Ms. Dargel seconded.
Roll as follows: Mr. Crowley,
yes; Ms. Dargel, yes; Ms. Robortaccio, yes.
BA-54-06 – CARLOS ORAMA –
VARIANCE FOR SIDE YARD SETBACK FOR ADDITION LOCATED ON KINGS HWY. BLOCK 10005,
LOT 9 IN R-3 ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP OF ROXBURY
RESOLUTION
WHEREAS,
the Board, after carefully considering the evidence presented by the applicant
and having conducted a public hearing has made the following factual findings:
1.
The applicants are the owners and
occupants of the single-family home on site.
2.
The subject premises are an
improved lot of approximately 24,000 square feet.
3.
The applicants were proposing to
construct an addition onto the existing home as depicted on the drawings
submitted with the application.
4.
The addition will add a garage and
master bedroom to the existing home.
5.
Applicant received a letter of
denial dated 7/26/06 from Tom Potere, the Zoning Officer.
6.
A side yard variance is needed for
the rear corner of the house because the house was constructed on an angle.
WHEREAS,
the Board has determined that the relief requested by the applicant can be
granted without substantial detriment to the public good and without
substantially impairing the intent and purpose of the Zone Plan and Zoning
Ordinance of the Township of Roxbury for the following reasons:
- The
Board finds that the encroachment into the side yard is reasonable due to
the angle on which the house is constructed.
NOW,
THEREFORE, BE IT RESOLVED by the Board of Adjustment of the Township of
Roxbury on the 16th day of October 2006 that the approval of the within
application be granted subject, however, to the following conditions:
- House
to be used solely as a single family home. The Zoning inspector shall
inspect the property, review the plans, and verify that it is and will
remain a single family dwelling.
- Addition
to be sized, constructed, and located as depicted on the plans submitted
with the application. Side yard relief (“left side”) is to permit sideyard
to be no less than seven feet as requested.
Mr. Crowley made a motion to
approve the resolution. Ms. Dargel seconded.
Roll as follows: Mr. Crowley,
yes; Ms. Dargel, yes; Ms. Robortaccio, yes.
BA-45-06 – CAROLANNE
DONNELLY – VARIANCE FOR SHED LOCATED ON ROGERS DRIVE, BLOCK 11805, LOT 16 IN
R-3 ZONE
RESOLUTION OF FINDINGS AND CONCLUSIONS
BOARD OF ADJUSTMENT
TOWNSHIP OF ROXBURY
RESOLUTION
WHEREAS, the Board, after carefully considering the evidence
presented by the applicant and having conducted a public hearing has made the
following factual findings:
- The
applicants are the owners and occupants of the single-family home on site.
- The
submitted premise is a corner lot with front yards on both Rogers Drive
and Curtis Road.
- The
applicant’s home actually faces Curtis Road though its mailing address is
Rogers Drive.
- The
applicant is proposing to construct a shed (8’x12”) in one of the front
yards as depicted on the plot plan submitted with the application.
- Applicant
received a letter of denial dated 5/16/06 from Tom Potere, the Zoning
Officer.
WHEREAS, the Board has determined that the relief requested
by the applicant can be granted without substantial detriment to the public
good and without substantially impairing the intent and purpose of the Zone
Plan and Zoning Ordinance of the Township of Roxbury for the following reasons:
1.
The Board finds that the property
is uniquely encumbered in that it is a corner lot with two front yards. One
yard is steeply sloped so that there is only one realistic location for the
shed to be situated.
2.
The shed is necessary because the
house is small with no other storage areas.
3.
The proposed relief is consistent
with the intent and purpose of the zone plan and zone scheme.
NOW,
THEREFORE, BE IT RESOLVED by the
Board of Adjustment of the Township of Roxbury on the 16th day of
October 2006 that the approval of the within application be granted subject,
however, to the following conditions:
1.
No water or electrical utilities
are to be provided to the storage shed.
2.
The shed shall be 8’x12’ and
located as depicted on the plot plan submitted with the application.
Mr. Crowley made a motion to approve
the resolution. Ms. Dargel seconded.
Roll as follows: Mr. Crowley,
yes; Ms. Dargel, yes; Ms. Robortaccio, yes.
Ms. Robortaccio announced
Application BA-63-06, Omnipoint, will not be heard and is carried to
12/11/06; Application BA-64-06, 109 Main St., will not be heard and is
carried to 1/8/07; Application BA-60-06, Beneduce, will not be heard and
is carried to 12/11/06.
AGENDA
BA-61-06 – GILBERT MULLER –
VARIANCE FOR REAR YARD SETBACK FOR ADDITION LOCATED ON BROOKSIDE RD. BLOCK
3504, LOT 4 IN R-2 ZONE
Vicky Muller was sworn in.
Gilbert Muller was sworn in.
Mr. Muller stated they have lived
in Roxbury for 27 years and would like to expand their family room so that they
can enjoy their expanded family. The addition will be 8’ x 20’. The location
for the addition was chosen because that is where the existing family room is
and there is no other place where they could put the addition.
Mr. Crowley said it looks like it
is an irregular lot.
Mr. Muller said it is. He also
stated it will be a one-story addition.
PUBLIC PORTION OPENED
No one stepped forward.
PUBLIC PORTION OPENED
No one stepped forward.
PUBLIC PORTION CLOSED
Mr. Crowley made a motion to
approve the application because of the size of the addition and the dynamics of
the lot. Ms. Kinback seconded.
Roll as follows: Mr. Crowley,
yes; Ms. Kinback, yes; Ms. Dargel, yes; Ms. Robortaccio, yes.
BA-58-06 - RON & DONNA
CARAS – VARIANCE FOR ADDITION LOCATED ON KINGSLAND ROAD, BLOCK 11002, LOT 30 IN
R-3 ZONE
Ron and Donna Caras were sworn
in. He stated we are trying to use this property on the lake and add a two-car
garage on the front to clean up the front area. We presently have to park on
association property. We want to put an additional bedroom over the garage and
want to bump out 10 feet to the rear for a dining room area. We are adding a
shed roof along the left side to protect the balcony and a second floor deck in
the rear to recover some of the deck that we would lose.
Mr. Caras stated the existing
covered porch will be extended to the front corner of the house to cover the
walkway to shield it from weather.
The Board members felt the
information submitted was not adequate for them to make a determination.
Mr. Crowley suggested the
applicant should submit one diagram that shows the existing conditions and what
is going to change.
Mr. Stern said typically the
Board members get architectural drawings and it is very helpful for the Board
to evaluate the application when you are requesting all these variances.
Ms. Dargel said there are 6
variances requested, and that is a lot.
Ms. Robortaccio said the
impervious coverage of 69% is a very big variance. The building coverage is
almost doubling. You might want to look at trying to reduce those.
Ms. Dargel stated on the survey,
there are dimensions missing for the lengths and widths of the buildings.
Mr. Crowley said one of the
things I will be looking for is an attempt to reduce the scope of the
variances. If that can’t be done, you will have to offer proofs as to why that
can’t be done.
It was determined the applicant
will return to the Board with more accurate and complete drawings.
PUBLIC PORTION OPENED
No one stepped forward.
PUBLIC PORTION CLOSED
The application was carried to
1/8/07.
Ba-59-06 – WILLIAM
STEVENSON – VARIANCE FOR SINGLE FAMILY HOME LOCATED ON HIGH ST. BLOCK 4001, LOT
31 IN R-3 ZONE
Attorney Larry Kron represented
the applicant. He stated this lot is an isolated lot in the R-3 zone. The
application is for a single family dwelling. There are variances required for
front yard setback; setback from the railroad tracks; and building coverage –
15.94% proposed, 15% required.
William Stevenson was sworn in.
Steven Smith, engineer for the
applicant, was sworn in.
Mr. Kron stated we have written
to the owner of the adjacent lots, and he has stated he is not interested in
purchasing property from us or selling property to us.
Mr. Crowley asked if this house
will line up with the house we gave a variance to a few months ago.
Mr. Smith referred to Exhibit
A-2, an enlargement of the tax map, showing the existing home on Lot 29, the
remains of the foundation on Lot 30. The blue shows the location of the house
approved in August on Lot 30. The green is the proposed house on our lot, Lot
31. On Lot 32, 33, and 34, I show the existing dwellings. On Lot 32 the house
is set back about 15 feet; on Lot 33 it is about 19 feet; on lot 34 it is about
21 feet. The existing house on Lot 31 is set back about 19 feet, and we
propose a 26 foot setback. The house on lot 30 is at 25 feet, and the house on
Lot 29 is at about 33 feet. The proposal is basically in keeping with the
homes in the area.
Mr. Smith stated the lot requires
15,000 square feet, and this lot is 12,896 square feet. The ordinance allows
for existing platted lots in existence, provided all yard requirements are
complied with. This lot was established as part of a subdivision in 1913. We
are complying with the lot width, side yard setback, rear yard setback. We are
requesting a variance for setback to the railroad right-of-way.
Mr. Smith referred to sheet 1 of
2 of the plans submitted to the Board and stated a minimum of 100 feet is
required from the railroad right-of-way. We propose a 60 foot setback to the
right-of-way. It is about 71 feet from the tracks. It would not be possible
for us to comply with the 100 foot setback. We also require a variance for
building coverage. 15% is the maximum allowed and we propose 15.9%. We are
proposing a two-story four bedroom dwelling with a 2-car garage. We believe
the excess building coverage is di minimus. For lot coverage we are
permitted 25% and are proposing 20.8%. We are doing an upgrade or renovation
of the area. As each of the homes is rebuilt or reconstructed, we are upgrading
the aesthetics of the neighborhood. We feel that by granting the variances
there would be no substantial detriment to the neighborhood or public good and
would not substantially impair the intent and purpose of the zone plan.
Mr. Smith said there are many
different housing styles in the neighborhood – capes, ranches, bilevels,
colonials. What we are proposing here is a two-story colonial. The home
proposed on Lot 30 was also a two-story colonial, but was front-to-rear, rather
than traditional colonial.
Ms. Dargel asked the square
footage of the house itself.
Mr. Smith said the footprint is
2,056 square feet. The living area is about 2,900 square feet. The plans
don’t show any provisions for a deck or shed.
PUBLIC PORTION OPENED
No one stepped forward.
PUBLIC PORTION CLOSED
Ms. Dargel made a motion to
approve the application. The placement of the house is very strategic, and the
size of the house is reasonable for the area and for the lot. Mr. Crowley
seconded.
Roll as follows: Ms. Dargel,
yes; Mr. Crowley, yes; Ms. Kinback, yes; Ms. Robortaccio, yes.
The meeting was adjourned by
motion at 8:15 p.m.
Dolores
A. DeMasi, Secretary
lm/